8.2.1.2 — Site Evaluation

Copied!
(1) A site evaluation shall be conducted on every site where a new or replacement sewage system is to be installed.
(2) The percolation time shall be determined by,
(a) conducting percolation tests, or
(b) classifying the soil according to one of the following methods,
(i) the Unified Soil Classification System as described in MMAH Supplementary Standard SB-6, “Percolation Time and Soil Descriptions”, or
(ii) the Soil Texture Classification as described in Chapter 3 of USDA, “Soil Survey Manual”.
(3) Where the percolation time is determined by a percolation test, there shall be a minimum of 3 locations selected, suitably spaced to accurately evaluate the leaching bed area, with the highest percolation time of the tests being used.
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.