Div. B › Part 8 › 8.7 › 8.7.3 — Absorption Trench Construction

8.7.3.1 — Length of Distribution Pipe

Copied!
(1) The total length of distribution pipe shall,
(a) not be less than 30 m when constructed as a shallow buried trench, or
(b) not be less than 40 m for any other absorption trench.
(2) Except as provided in Sentences (1), (3), and (4) every leaching bed constructed by means of absorption trenches shall have a total length of distribution pipe not less than the value determined by the formula,
L=QT/200
where,
L =total length of distribution pipe in metres,
Q =the total daily design sanitary sewage flow in litres, and
T =the design percolation time.
(3) Except as provided in Sentence (1), where a leaching bed receives effluent from a Level II, Level III or Level IV treatment unit as described in Table 8.6.2.2., the leaching bed may have a total length of distribution pipe not less than the value determined by the formula,
L=QT/300
where,
L =total length of distribution pipe in metres,
Q =the total daily design sanitary sewage flow in litres, and
T =the design percolation time.
(4) Except as provided in Sentence (1), where the leaching bed is constructed as a shallow buried trench, the total length of the distribution pipe shall not be less than the value determined by Table 8.7.3.1.
Tables & Figures referenced
Table 8.6.2.2 : Other Treatment Unit Effluent Quality Criteria : Forming Part of Sentences 8.6.2.2.(1) and (2)
Loading Table 8.6.2.2…
Table 8.7.3.1 : Length of Distribution Pipe in Shallow Buried Trench : Forming Part of Sentence 8.7.3.1.(4)
Loading Table 8.7.3.1…
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.