Div. B › Part 8 › 8.7 › 8.7.2 — Design and Construction Requirements

8.7.2.2 — Distribution Pipes within Leaching Beds

Copied!
(1) Sentence (2) applies to the design and construction of a leaching bed with distribution pipes used within the leaching bed.
(2) The header line and distribution pipes within a leaching bed shall be designed and constructed so that they can be detected by,
(a) magnetic means,
(b) means of a 14 gauge TW solid copper light coloured plastic coated tracer wire, or
(c) other means of subsurface detection.
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.