9.16.4.2 — Topping Course

Copied!
(1) Where a topping course is provided for a concrete floor slab, it shall consist of 1 part cement to 2.5 parts clean, well graded sand by volume, with a water/cement ratio approximately equal to that of the base slab.
(2) When concrete topping is provided it shall not be less than 20 mm thick.
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.