Div. B › Part 9 › 9.29 › 9.29.5 — Gypsum Board Finish (Taped Joints)

9.29.5.10 — Low Temperature Conditions

Copied!
(1) In cold weather, heat shall be provided to maintain a temperature of not below 10°C for 48 h prior to taping and finishing and maintained for not less than 48 h after that.
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.