Div. B › Part 9 › 9.22 › 9.22.9 — Clearance of Combustible Material

9.22.9.4 — Heat Circulating Duct Openings

Copied!
(1) The clearance of combustible material above heat circulating duct openings from those openings shall be not less than,
(a) 300 mm where the combustible material projects not less than 38 mm from the face, and
(b) 150 mm where the projection is less than 38 mm.
Disclaimer. This site provides general access to Ontario Building Code information for reference only. It is not an official source and may omit or summarize content. Always verify requirements with the current OBC and your Authority Having Jurisdiction (AHJ). The Ontario Building Code is Crown copyright © King’s Printer for Ontario. Terms of Use.